Update: March 14, 2022
Sewer main work has started at the North end of Riverside Blvd. This work, ultimately connecting at Broadway, will continue for the next 2-3 months. Closures and detours in these areas should be expected and will be coordinated with the city as needed. Foundation piles are complete and the pile rig has been removed from the site. Concrete work for the foundation continues to progress across the site. The podium/ parking garage has started to go vertical in the eastern portion of the project. At the current pace we anticipate the complete podium/ parking garage to be complete by early fall. Construction of Tower C, the rental building, should commence in mid-April and top off by years end.