Update: January 9, 2022
On-site removals of fill and debris is expected to be complete within the next 2-3 weeks. Residents should start to see a decrease in trucks entering and leaving the site related to this work this week. The install of the CFA piles is still ongoing, this work expected to wrap-up by the middle of February. Concrete work ( pile caps, grade beams and columns ) has started in the north and southeastern portion of the site. This work will be ongoing for the next few months. Deliveries associated with this work have been utilizing the Long Beach Blvd. closure and will continue to do so over the next few weeks. Sewer main work will commence next week and the work should take about 3 months to complete. This work has been, and will continue to be, coordinated with DPW and LBPD.