Update:December 19, 2021
Supporting watermain work will continue for the next week along East Broadway and along Long beach Blvd. Closures and detours in these areas should be expected and will be coordinated with the City as needed. On site removals of fill and debris will be on going as will the install of the CFA piles. Concrete work ( pile caps and grade exams ) has started In the north eastern portion of the site. This work will be one ongoing for next few months .The closures of Riverside and Long Beach Blvd are in place and working well.